We specialise in developing photovoltaic projects – from the leasing of land to obtaining connection conditions.
We would like to invite complex project development companies and partial services such as land leasing, interested in establishing a business relationship.
We offer support in the settling the fees for the issuance of connection conditions and the preparation of projects to participate in the RES auction organised by the Energy Regulatory Office.
Provides the right to administer the estate. Specific location requirements must be met for the construction of a solar farm.
It includes visualisation, investment description, cost estimate. It gives you an opportunity to apply for grants.
Required for an area over 0.5 ha (protected site) or 1 ha (other)/ It takes approximately 4-6 months to obtain it.
Required in the absence of a local spatial development plan. It takes 3-5 months to obtain them.
These are issued by the distribution network operator within 120 days from the submission of the connection application.
Signed between the developer and the distribution network operator within approx. 2 months after the issue of the connection conditions.
Required to start construction of the installation. Depending on the complexity of the project, it can take from one to several months to obtain the permit.
The time needed to build an average-sized 1MW PV farm, from the very beginning of construction to its formal completion, i.e. obtaining an occupancy permit, is about 7 months.
This is granted by the energy regulatory authority.
Remote support and service.
We can handle the process of selling energy.